Consultancy service for ESIA, RAP, Stakeholder Engagement and Supervision of E&S Safeguards for the Latoro Small Hydropower Project in Nwoya District

Client East African Power Ltd
Funder Equity Bank
Project Cost USD 670,000
Status Completed
Water and Energy Infrastructure

ESIA, RAP and E&S safeguards supervision for the Latoro small hydropower project.

Key Activities

  • Carrying out environmental screening and impact assessment for civil works and transmission line routing.
  • Consulting local communities, local government officials, and cultural institutions.
  • Formulating compensation frameworks and resettlement strategies.
  • Supervising environmental compliance during project construction.